Tadadi Port

KSIIDC as designated as the nodal agency for development of a Sea port at Tadadi on PPP basis. Following is the status of the project:

  • KSIIDC has incorporated a special purpose company viz., “Tadadi Port Limited” paid up Capital – Rs. 5.00 lakhs.

Status of Project

  • About 1420 acres of land available for Port
  • Detailed Feasibility Report (DFR) – prepared by Consortium of M/s Prointec (Spain) and M/s Mir Projects & Consultants

Ultimate capacity of 62.36 mtpa (8 berths); Estimated project cost – Rs. 4318 crore (2017 rates).

3. EIA and CRZ Studies – by National Environment Engineering & Research Institute

  • CRZ clearance – Obtained
  • EIA report & also additional studies report submitted to MoEF & CC.
  • MoEF & CC – Environmental Clearance.
    • Expert Appraisal Committee (EAC) has recommended for Environment Clearance with certain conditions (27 No’s), including Stage – I Forest Clearance & valuation of bivalves in the estuary region.
    • Study on valuation of bivalves – Department of Studies in Marine Biology, Karwar. Report is ready.
    • Stage – I Forest clearance for about 200 hectares of mangroves – awaited.

4. Bid documents are under finalization by iDeCK (TA).

On obtaining forest and environmental clearances, tendering process (RFQ) will be initiated.